Environmental movements presented data in favor of alternative routes to build the bridge. The debate around the use of public transport and railways expanded.



Description:

In 1991, the Government of Portugal created a new department for managing the construction of the new crossing of the Tagus River at Lisbon called GATTEL. The office identified three potential corridors for the new road bridge: eastern (Sacavém-Montijo), central (Chelas-Barreiro), and western (Algés-Trafaria).

See more
Basic Data
Name of conflict:Movement against the location of the Vasco da Gama bridge in Lisboa, Portugal
Country:Portugal
State or province:Lisboa
Location of conflict:Lisboa
Accuracy of locationHIGH (Local level)
Source of Conflict
Type of conflict. 1st level:Infrastructure and Built Environment
Type of conflict. 2nd level:Transport infrastructure networks (roads, railways, hydroways, canals and pipelines)
Specific commodities:Land
Asphalt
Transport services
Project Details and Actors
Project details

It is the longest main bridge in Europe (including viaducts) with a total length of 17.2 kilometres (10.7 mi)), including 0.8 kilometres (0.50 mi) for the main bridge, 11.5 kilometres (7.1 mi) in viaducts, and 4.8 kilometres (3.0 mi) in dedicated access roads.

See more
Project area:17,2 km
Level of Investment for the conflictive project1,107,650,000
Type of populationUrban
Start of the conflict:01/01/1991
Company names or state enterprises:Consórsio Lusoponte (Lusoponte) from Portugal
Relevant government actors:Gabinete de Travessia do Tejo em Lisboa (GATTEL)
Comissão de Acompanhamento da Obra (CAO)
Ministérios do Planejamento, Ambiente, Indústria, Emprego, da Defesa e da Justiça
Environmental justice organizations (and other supporters) and their websites, if available:Associação de Montijo e Alcochete para a Defesa da Qualidade de Vida (AMA)
Associação Nacional de Conservação da Natureza (Quercus)
Grupo de Estudo de Ordenamento do Território e Ambiente (GEOTA)
Instituto Dom Dinis (IDD)
Liga de Proteção da Natureza (LPN)
World Wild Fund For Nature (WWF)
Conflict & Mobilization
IntensityMEDIUM (street protests, visible mobilization)
Reaction stagePREVENTIVE resistance (precautionary phase)
Groups mobilizing:International ejos
Local ejos
Local scientists/professionals
Forms of mobilization:Development of alternative proposals
Lawsuits, court cases, judicial activism
Objections to the EIA
Official complaint letters and petitions
Impacts
Environmental ImpactsVisible: Air pollution, Noise pollution
Potential: Biodiversity loss (wildlife, agro-diversity), Reduced ecological / hydrological connectivity
Outcome
Project StatusIn operation
Conflict outcome / response:Institutional changes
Strengthening of participation
Application of existing regulations
Proposal and development of alternatives:Environmental movements presented data that favored other corridors to build the bridge. The debate around the use of public transport and railways expanded.
Do you consider this an environmental justice success? Was environmental justice served?:Not Sure
Briefly explain:The route in which the bridge was built was the one contested by the NGOs. However, the intervention by them helped expand their participation in decision-making process and in the construction monitoring committee, which allowed them to directly challenge the actions and omissions as to the EIA.
Sources & Materials
References to published books, academic articles, movies or published documentaries

GARCIA, José, L.; SUBTIL, Filipa. Conflito social e ambiental – a ponte Vasco da Gama. Análise Social, v. 33, p. 707-746, 1998.
[click to view]

MELO, João Joanaz. The Vasco da Gama Bridge on the Tagus Estuary: A paradigm of bad decision making, but good postevaluation, World Transport Policy & Practice. Volume 6, n.2. 2000
[click to view]

FICHA SINTÉTICA E DE IDENTIFICAÇÃO - Concessão Lusoponte
[click to view]

NEW

PAeM – Vídeos sobre as pontes do rio Tejo
[click to view]

LUSA. Ponte Vasco da Gama foi construída há 10 anos. Jornal Público. Nacional, 25 de Março de 2008.
[click to view]

Related media links to videos, campaigns, social network

REMOVE

Vasco da Gama bridge
[click to view]

Meta information
Contributor:Francisco Fernandes, Inês Ribeiro and Sofia Bento
Last update18/08/2019
Conflict ID:1690
Comments
Legal notice / Aviso legal
We use cookies for statistical purposes and to improve our services. By clicking "Accept cookies" you consent to place cookies when visiting the website. For more information, and to find out how to change the configuration of cookies, please read our cookie policy. Utilizamos cookies para realizar el análisis de la navegación de los usuarios y mejorar nuestros servicios. Al pulsar "Accept cookies" consiente dichas cookies. Puede obtener más información, o bien conocer cómo cambiar la configuración, pulsando en más información.